PROCEDURE TO PROCESS AN UNSOLICITED PROJECT PROPOSAL RECEIVED UNDER PUBLIC PRIVATE PARTNERSHIP AUTHORITY (AMENDMENT) ACT 2021

PROCEDURE TO PROCESS

AN UNSOLICITED PROJECT PROPOSAL RECEIVED UNDER PUBLIC PRIVATE PARTNERSHIP AUTHORITY (AMENDMENT) ACT 2021

S. No

Task

Responsibility

Timeline

1

USP received in Pakistan Railways Headquarters/Ministry of Railways

-

Zero day

2

Appraisal by Pakistan Railways  

Relevant officers from MoR and PR

10 days

3

Comments/observations conveyed to unsolicited proponent for revision

DD/PPP

2 days

4

Revision by unsolicited proponent

Unsolicited proponent

7 days

5

Project proposal presented to Executive Committee (EC) for assessment of viability

Executive Committee

2 days

6 (a)

If project declared viable by EC, forwarded to P3A for appraisal

P3A

10 days

6 (b)

If declared unviable, same will be communicated to unsolicited proponent

DD/PPP

2 days

7 (a)

In case of qualified project: USP approved for open competitive bidding

P3A Board

 

 

7 days

 

7 (b)

In case of non-qualified project: USP approved for open competitive bidding

SRCM

8

Project advertised for open competitive bidding under PPRA Rule 37(A)

PR HQs

  • National competitive bidding:15 days
  • International Competitive bidding: 30 days